Mayo no events posted in last week
The Wholesome Photo of the Month Thu May 09, 2024 11:01 | Anti-Empire
In 3 War Years Russia Will Have Spent $3... Thu May 09, 2024 02:17 | Anti-Empire
UK Sending Missiles to Be Fired Into Rus... Tue May 07, 2024 14:17 | Marko Marjanović
US Gives Weapons to Taiwan for Free, The... Fri May 03, 2024 03:55 | Anti-Empire
Russia Has 17 Percent More Defense Jobs ... Tue Apr 30, 2024 11:56 | Marko Marjanović Anti-Empire >>
A bird's eye view of the vineyard
Alternative Copy of thesaker.is site is available Thu May 25, 2023 14:38 | Ice-Saker-V6bKu3nz Alternative site: https://thesaker.si/saker-a... Site was created using the downloads provided Regards Herb
The Saker blog is now frozen Tue Feb 28, 2023 23:55 | The Saker Dear friends As I have previously announced, we are now “freezing” the blog. We are also making archives of the blog available for free download in various formats (see below).
What do you make of the Russia and China Partnership? Tue Feb 28, 2023 16:26 | The Saker by Mr. Allen for the Saker blog Over the last few years, we hear leaders from both Russia and China pronouncing that they have formed a relationship where there are
Moveable Feast Cafe 2023/02/27 ? Open Thread Mon Feb 27, 2023 19:00 | cafe-uploader 2023/02/27 19:00:02Welcome to the ‘Moveable Feast Cafe’. The ‘Moveable Feast’ is an open thread where readers can post wide ranging observations, articles, rants, off topic and have animate discussions of
The stage is set for Hybrid World War III Mon Feb 27, 2023 15:50 | The Saker Pepe Escobar for the Saker blog A powerful feeling rhythms your skin and drums up your soul as you?re immersed in a long walk under persistent snow flurries, pinpointed by The Saker >>
Interested in maladministration. Estd. 2005
RTEs Sarah McInerney ? Fianna Fail supporter? Anthony
Joe Duffy is dishonest and untrustworthy Anthony
Robert Watt complaint: Time for decision by SIPO Anthony
RTE in breach of its own editorial principles Anthony
Waiting for SIPO Anthony Public Inquiry >>
Indymedia Ireland is a volunteer-run non-commercial open publishing website for local and international news, opinion & analysis, press releases and events. Its main objective is to enable the public to participate in reporting and analysis of the news and other important events and aspects of our daily lives and thereby give a voice to people.
Julian Assange is finally free ! Tue Jun 25, 2024 21:11 | indy
Stand With Palestine: Workplace Day of Action on Naksa Day Thu May 30, 2024 21:55 | indy
It is Chemtrails Month and Time to Visit this Topic Thu May 30, 2024 00:01 | indy
Hamburg 14.05. "Rote" Flora Reoccupied By Internationalists Wed May 15, 2024 15:49 | Internationalist left
Eddie Hobbs Breaks the Silence Exposing the Hidden Agenda Behind the WHO Treaty Sat May 11, 2024 22:41 | indy Human Rights in Ireland >>
|
Corrib Truth - Overdue
mayo |
environment |
press release
Sunday August 28, 2005 16:52 by JM Rossport South, Ballina, Co. Mayo, Ireland
![Report this post to the editors Report this post to the editors](../graphics/report.gif)
A response to the powerful lies behind Corrib’s Unnatural Gas
The proposed gas pipeline in Erris, County Mayo, has at various times been referred to as either a transmission, distribution, domestic, offshore, sales or upstream pipeline, and even “offshore landline”. One thing is certain; no-one outside of the Shell/Statoil/Marathon partnership can take responsibility for the safety of the public. This is the number one concern for the people of Rossport. Pipeline Design
The pipeline design was never evaluated by any competent authority, having been deemed, by Mayo County Council at the developers request, to be “exempt” from planning. The gas Refinery at Bellanaboy was turned down twice at the planning stages, but An Bord Pleanála eventually gave it the green light, overruling its own Senior Inspector who thoroughly condemned the project on a number of grounds.
The pipeline has from the very start been designed to withstand an operating pressure of 345 bar. Neither the design nor gas field have changed, but the stated operating pressure has dropped through 272 bar, 150 bar and 120 bar, to a recent figure of 100-110 bar, without any scientific basis.
The critical figure used to calculate various aspects of the pipeline, known as the
Maximum Allowable Operating Pressure (MAOP), has never been openly stated.
The design code used by the engineers to achieve the pipe wall thickness of 27.1mm (1.07”) is the British BS8010, which is now out of date. This also happens to be the thinnest pipe allowable under that code, and ignores the need for 62mm (2.44”) at road crossings because of “difficulty in welding”.
Safety Distances
Design codes use the pipeline MAOP to determine the minimum safety distance to houses. The closest figure to this has been the often-repeated Maximum Operating Pressure (MOP) of 150 bar, which would result in a minimum clearance using BS8010 of 84m (273 ft).
The actual pressure that will be reached, and MUST be taken for safety reasons, is 345 bar, resulting in a clearance of 170m (553 ft). The safer Canadian/American model says this distance should be 295m (959 ft).
The houses in Rossport will barely be 70m (227 ft) away, and in several cases people will have to cross over the pipeline just 1.2m (4 ft) underground to get in and out of their homes every day.
This could never truthfully be described as “the highest possible safety standards”.
Waste Water
The outfall pipe takes waste products not recoverable from the gas treatment process and transports them 12.7km for discharge into Broadhaven Bay, home to nine confirmed species of whale and dolphin right up to Orcas; top of the food chain.
This discharge will contain varying amounts of the following; Chlorides, Sulphates, Bicarbonates of Sodium, Potassium, Calcium, Magnesium, Iron Hydroxide, Calcium Sulphate, Radon, hydrocarbon condensate, Methanol, corrosion inhibitor, well completion muds, scale inhibitor, anti-foam, heating medium, lube oils, descaling fluids, and up to 3 tons of Lead, Nickel and Mercury every year.
Other elements to be found include Barium, Boron, Phosphorous, Chromium, Manganese, Copper, Zinc, Arsenic, Selenium and Silver … this will not be “drinking water “.
Air Pollution
On top of all the waste water pollutants, the air in the vicinity of the refinery will be poisoned by Oxides of Nitrogen, Oxides of Carbon, particulate matter, Volatile Organic Compounds, Methane, Sulphur Dioxide, and POCP emissions including Ethane, Propane, i-Butane, n-Butane, i-Pentane, n-Pentane, n-Hexane, n-Octane, n-Heptane and Methanol.
Safety Reviews
Two so–called “independent” safety reviews of the pipeline design have been carried out so far … both by companies with close ties to Shell.
Neither review covered the whole concept for this unique and experimental project, the “subsea tie-back” solution, alternatives to which have never been satisfactorily explored.
Incredibly a third review has been ordered by Minister Noel Dempsey, but this underlying problem is yet again not to be addressed.
Quotes
“The design of this pipeline is a totally different design”
MD Shell E&P Ireland Limited, Andy Pyle, denying the “upstream” section is comparable to gas transmission pipelines (RTE Radio1 06/08/05)
“.. this is a transmission pipeline.”
Corrib Operations Manager, Mark Carrigy (“Countryfile” BBC TV 07/08/05)
|